The first aggregate of the Bureiskaya hydropower station (south of the Khabarovsk Territory) is ready to be tested on no load. The appropriate act was signed by the operators and the administration of the station under construction.
The press service of the Bureiskaya hydropower station reported on Monday that its test commissioning will be conducted during a week.
The filling of the turbine water line began on Monday. Through it, water will be supplied from the upper pond of the dam to the working wheel of the turbine.
Finishing work has been completed in the machine department of the hydropower station. The state commission will soon examine the premises.
The commissioning of the first aggregate of the Bureiskaya hydropower station for permanent exploitation will take place on June 30, the press service reported